Work is being done by American Transmission Co. on the Riverside Transmission Line project, an approximately 4.2-mile project consisting of two circuits of 345,000-volt transmission line. The line will connect a new substation near the Alliant Energy West Riverside Energy Center to an existing 345,000-volt transmission line in town of Beloit.

The foundation installation for the new line, consisting of 30 structures, is expected to be completed this month. Pole installation will follow in December with the line expected to be energized by mid-2019.